The Leprosy Project
The goal of The Leprosy Project is to see the villages we serve free from leprosy and fully accepted into society.
  • Home
  • Programs
    • Prevention of Disabilities
    • Prosthetics Protection
    • Nutrition and Hygiene
    • Environment, Infrastructure & Community Development >
      • The Water Project
      • Update - Yanyuan Water Project
      • Update - Butuo Water Project
      • Update - Jinyang Water Project
    • Children's Education
    • Public Awareness
  • Villages
    • Butuo
    • Ganluo
    • Huidong
    • Huili
    • Jinyang
    • Leibo
    • Luding
    • Mianning
    • Meigu
    • Muli
    • Puge
    • Xide
    • Yanbian
    • Yanyuan
    • Yuexi
    • Zhaojue
  • Photo
  • News
  • Governance
    • Accounts
    • Project Reports
    • Volunteer Board of Directors
  • Acknowledgement
    • 2021
    • 2020
    • 2019
    • 2018
    • 2017
    • 2016
    • 2015
    • 2014
    • 2013
    • 2012
    • 2011
    • 2004-2010
  • Contact Us

UPDATE on jinyang water project 

Picture
Background:
​
The Leprosy Project began surveying the area around the villages of Butuo and Jinyang in late March, 2015.  The final plan for both phases of the water project in Jinyang was confirmed in the summer 2016.  We commenced the Jinyang Water Project in December 2016 after the Butuo Water Project was completed.
 
After 5 months of hard work, the long-awaited water project in Jinyang was completed with the final installation of the drip irrigation system for the home vegetable gardens for all households. The Leprosy Project invested a total of RMB263,445 in the water project, which involved more than 1500 work trips by the villagers who were required to be involved in both the planning and implementation.
 
A 60M³ GRP sectional water storage tank for irrigation water was placed in the village and 3 concrete sediment tanks were constructed at the water source.  Existing concrete tanks were also repaired.  The whole installation included 14,680 meters of pipes. Vegetable gardens covered by the drip irrigation system now cover 3.8 mu and serve the entire village including the school. Every home has water taps installed. 
 
More than 75% of the farmland in the village is covered by the new water system. This totals approximately 315mu, including 20mu of paddy fields. These fields belong to the 163 villagers who live in three village clusters.  This is the second-largest water project that The Leprosy Project has implemented.
Picture
Delivery of panels of water tank to the village
Conditions at the construction site:
Access to the village is via steep and narrow paths. The delivery of the water pipes, panels for the water tanks and other heavy equipment was difficult and dangerous. Six truckloads were delivered to the top of the mountain above the village. Materials were then transported by foot down to the village, a three hour trek.
  • Beneficiaries
All villagers from the 3 clusters of Xihe Village (Jinyang) benefited from the water project which now provides a year around supply of water for          drinking, irrigation and livestock
Source for drinking water is located behind the mountain.
Villagers offloading water pipes and material for the water project.
  • Difficulties in implementing the project
The route of main water pipes are located on steep cliffs. Connecting the pipes on these slopes was difficult and dangerous. Falling stones were a hazard. Villagers secured themselves to trees and rocks in order to install the water pipes. When neither were available they drilled into the rock to secure themselves before installing the pipes.  Fifteen years ago, during the construction of the old water system by the PLA, a horse and a villager fell down the mountain. Project staff and villagers were alerted about safety during the implementation phase. Safety equipment was provided to ensure no one was hurt during the construction.​
Villagers doing construction work on the steep mountainside.
Villagers doing construction work on the steep mountainside.
  • Drinking water
The first phase of the project was to provide drinking water. A total of 3452 meters of main pipe were connected from the water source to cluster 3 at the top of the village. Pipes were then connected to provide drinking water for clusters 1 and 2.  Each household now has a water tap and basin installed. This insures water is available to each household, especially during the dry season from October to April.
Villagers had to work at dangerous locations on the mountain during the construction period
Villagers had to work at dangerous locations on the mountain during the construction period
Heavy water pipes were carried up and down the moutain manually to the water source
Heavy water pipes were carried up and down the moutain manually to the water source
Finally, drinking water was connected to the village, taps and basins are installed in the courtyard of every household.
Finally, drinking water was connected to the village, taps and basins are installed in the courtyard of every household.
  • Irrigation water
The second phase was aimed at improving the irrigation system for the entire village. The goal was to increase production of crops from 1 to 2 harvests per year, promote a variety of vegetables that could be grown in home gardens (using the drip irrigation) and improving the nutrition of villagers, especially the children, with a wider variety of vegetables.  Four thousand one hundred thirty meters of main water pipes were connected from the water source to the water distribution section. Water tanks store the irrigation water.
 
  • Paddy fields
All the paddy fields were flooded in early April. In the past this would not happen until June. This means villagers can harvest their rice at least two months earlier.
 
  • Home vegetable gardens
The drip irrigation systems ensures water is efficiently used. The system also saves significant of time and effort on the part of the villagers.
Villagers carrying water pipes and other heavy equipment to the construction site
Villagers carrying water pipes and other heavy equipment to the construction site
Villagers carrying water pipes and other heavy equipment to the construction site
Villagers carrying water pipes and other heavy equipment to the construction site
  1. Input of the project

Input and beneficiaries of the Jinyang Water Project
Total Investment:  RMB263,444.66
1 GRP Sectional Water Tanks:  Total storage of 60 Cubic Meter
3 Concrete Water Tanks: Total storage of 22 Cubic Meter
160mm PE Pipes: 3250M
110mm PE Pipes: 1280M
50mm PE Pipes: 3950M (500M shall be connected after the road construction has been finished)
32mm PE Pipes: 1700M
25mm PE Pipes: 400M (shall be installed after the road construction has been finished)
20mm PE Pipes: 5000M
Labour Input: More than 1500 work trips by villagers
Results and beneficiaries:
  1. All 163 villagers from 41 village households, school and the clinic.
  2. 100% of households installed with water taps at home.
  3. Total 340mu (75%) of dry land can be irrigated.
  4. 20mu (100%) of paddy fields can be irrigated.
  5. 100% of family vegetable fields are covered.
  6. More than 75% of farming land is covered with the new irrigation system overall.  Some villagers who are working outside the village have contacted us saying they would like to come back to the village to farm now there is a new water system.
Source of irrigation water
Catchment tank
Pipe welding machine
Welding pipes together
Technical involvement 
  • The GRP Sectional Tank was chosen for the project because it is durable, flexible and it comes in panels that can be assembled on site. With this tank we were able to install the size of tank needed for the location. There were, however, many challenges in delivering the panels to the site. 
 
  • The GRP Sectional Tank is not known in Liangshan. We had to invite an instructor from the manufacturer in Shandong to instruct and guide the villagers on how to assemble the tank.  This was important for future maintenance of the tank.
Concrete platform for water tank
Villagers welding the metal frame for the tank
  • We invited villagers from Jinyang to learn how to install and connect water pipes last year during the implementation of the water project in Butuo. Villagers gained valuable experience in overcoming the difficulties of working on dangerous cliffs and slopes.  Some of the experienced villagers from Butuo also helped in the pipe connection work in Jinyang.  Their work was highly praised by the technicians from the supplier of the water pipes who came to inspect the work.
Villagers helped install the water tank
GRP sectional water tank successfully installed
​
  • The water sources are quite dispersed. This necessitated villagers building small channels which fed into a large channel before emptying into the sediment tank. From the sediment tank water was piped to the village. The sediment tank not only acts as a filter, but also reduces the pressure preventing pipes being broken due to strong water pressure from the source especially during rainy season.
 
  • Two demo vegetable gardens with drip irrigation systems were set up, one in cluster 3 and one at the school which is located in cluster 1.  The vegetable gardens were very successful.  With another round of funding designated for the drip irrigation, The Project has been installing systems in all the home vegetable gardens in both Butuo and Jinyang. This will soon be complete. Some of the villagers who are working outside also asked the project to install the system in their gardens. They would like to return home and farm with the brand new water system.
Veggie garden with drip system at the school
Paddy fields flooded with water
Plans for the community 

In the past, villages suffered from drought at least 6 months every year. Now they have a consistent source of water flowing out of their taps. Their quality of life has improved significantly.
 
  • To promote the drip irrigation system for their home vegetable gardens. The produce is for their own consumption.
  • To extend the variety of crops and vegetables in order to improve their nutrition and living standards as well as provide extra income.
  • To extend another 15-20 mu of paddy fields in next three years after the road construction to the village is completed.
  • To plant a variety of fruit trees and trees for income generation, using the support from local forestry department.
Villagers had to live and cook in the wild during the entire construction work in order to save travelling time.
Villagers had to live and cook in the wild during the entire construction work in order to save travelling time.
Project Expenses ​
Description
Transportation
Delivery of water pipes, water tank parts, and other parts needed for the project
 
Insurance
For volunteer labor input
 
GRP Sectional Tanks and concrete platform
one 60M³ sectional tank with concrete platform and metal frame
 
Sediment tanks and reparation of existing concrete tanks
Materials such as cement, sand, reinforced steels

Water Pipes and Necessary Accessories
From 20mm to 160mm PE pipes and pipes for drip system of the demo vegetable gardens, different connectors, valves, etc
 
Technician Fees
Installing of GRP tanks, including accommodation and meals

​Total Expenses:
​Amount in RMB
​19,337.00



2,200.00


26,058.00



16,322.00


197,636.66



1,891.00
​​​

​263,444.66

Powered by Create your own unique website with customizable templates.